A three-story structure at 1321 Flatbush Avenue collapsed Wednesday afternoon, injuring 17 people and exposing the upper floors of the adjacent property.

By Enzo Melnyk ·

Illustration for: Brooklyn building falls into excavation pit, killing eight in Flatbush
Illustration generated for this article, not a news photograph.

A three-story building in Brooklyn’s Flatbush neighborhood crumbled into a neighboring construction pit on Wednesday afternoon, killing at least eight people. The structure at 1321 Flatbush Avenue contained a retail store on the ground floor and apartments above. When it gave way, it plunged into an active excavation site, sending debris and dust across the block.

New York Police Department records show the first emergency call came in at 4:01 p.m. Eastern Time. Firefighters arrived within a minute of the initial collapse, aided by units already stationed nearby. By 4:03 p.m., the city’s Notify NYC system sent alerts to residents about heavy emergency traffic and road closures. Within thirty minutes, reports confirmed that people were trapped beneath the rubble, launching a large-scale rescue effort.

The force of the collapse damaged the property next door at 1323 Flatbush Avenue. A wall of that building was torn away, leaving its stairwells and apartments exposed to the weather. Crews worked through the night to pull survivors from the wreckage. At 6:15 p.m., firefighters broke through a collapsed wall and found a conscious, dust-covered woman. A husband who had been searching for her told reporters she was pregnant and had survived.

Mayor Zohran Mamdani addressed the public at 9:03 p.m. to confirm the initial toll. At that time, he reported two deaths and 17 injuries. By Thursday morning, the death count had risen to at least eight. The mayor said he was heartbroken by the loss of eight New Yorkers and extended condolences to the families of the deceased and the injured.

Scrutiny has turned to the construction activities at the nearby site. Developers at 2625 Bedford Avenue held permits for excavation and foundation work for a new three-story building. The Department of Buildings issued a stop work order in March after inspectors found they had demolished an existing building without providing adequate shielding to neighboring properties. Despite the order, demolition work continued for a short period, resulting in a $10,000 fine. The stop work order was lifted in May once the developers demonstrated compliance with safety regulations.

The incident has intensified questions about oversight of construction sites in densely populated areas. Investigations into the cause of the collapse have begun. The city is working to support those affected as the rescue operation continues.

More News · National news · Report a business · Got a Story?

Get Hot Report Digest in your inboxCity news, clearly told. Free, a few times a week, unsubscribe any time.

Related stories

Get Hot Report Digest in your inboxCity news, clearly told. Free, a few times a week, unsubscribe any time.